Objective:
- If I have a completed task will I still be reminded?
- Do I still get reminders for completed Tasks?
Environment:
- Clio Manage
Additional Information:
If a Matter is closed and the Task has not yet been completed then you will still receive reminders until it is marked as completed.
Answer:
No, if you complete the Task before the Reminder is supposed to be delivered, you will not receive the Reminder.