KCS - Can I Change the Due Date of an Entire Task List Once It Has Been Assigned?

Objective:

  • Bulk edit task list date change 

Environment:

  • Clio Web App

Additional Information:

See here for more information task dependencies.

Answer:

Once a Task List is assigned, individual Tasks are created for the Assignee. You would have to individually Edit each Task to change the due dates.

However, if your task list contains Task Dependencies, then you can change the due date of all dependent Tasks by changing the date of the Task they are dependent on. 